Skip to content

City Officer: Lee, Edwin – Mayor – Filed: March 23, 2015 – Contractor: McGuire and Hester

Nature of Contract

Public Works executed a contract with McGuire and Hester to complete preparatory infrastructure work related to underground utilities for the temporary structures which will comprise the barracks, operation center and vehicle garage for Treasure Island Fire Station.

Date Contract Approved

March 19, 2-015

Amount

$259,892.00